Municipal Regional Permit Provision C.3 and C.6
Compliance Inspection and reporting
Construction General Permit (CGP) Stormwater Compliance
Industrial General Permit (IGP) Stormwater Compliance
MRP C.3 Provision Experience
Completed inspection and verification of proper
installation of more than 75 stormwater treatment systems
comprising of bioswales, bioretention areas, flow through
planters; roof gardens; permeable pavers; and vault-based
systems, etc.
Completed O & M inspections of bioswales, bioretention
areas, flow through planters, retention ponds, constructed
wetlands, infiltration galleries, permeable pavers and vault
based systems
Completed O & M inspections of more than 75 treatment
systems
Completed O & M inspections of stormwater treatment
systems on more than 30 sites
Prepared O & M plan for stormwater treatment systems
Prepared annual reports
MRP C.6 Provision Experience
Completed Inspections on Over 250 Sites
Completed more than 1,500 C.6 Provision Inspections
Prepared Approximately 100 Different types of Enforcement Letters
Prepared Numerous Annual Reports
Services - Construction General Permit
Performing run-on and run-off calculating
Preparing and implementing SWPPPs
Preparing and implement WPCPs
Calculating Project Risk Level using the revised
universal soil loss equation and sediment load in the receiving
water body
Implementing best management practices (BMPs)
Conducting site inspections and reporting
Have completed more than 1000 site inspections
Uploading data into the State Water Resources Control
Board Stormwater Multi Application, Reporting and Tracking System
Field Sampling and analysis
Preparing Quality Assurance Project Plans for field
sampling and analysis
Conducting field sampling using pH and turbidity meters
as well as the United States Environmental Protection agency
methods for performing various laboratory analysis
Preparing corrective measures reports
Conducting chemical loading calculations
Assessing enforcement measures for implementing
compliance activities
Use of CASQA and Caltrans SWPPP Templates
Preparing Annual Summary Reports
Preparing groundwater dewatering plans
Preparing creek diversion/bypass system plans
Preparing specifications for WPCP, SWPPP for Risk Level
1, 2 and 3 and active treatment systems.
Construction General Permit - Project Experience
1501 California Ave, Palo Alto, California, November 2014
- Ongoing.
Stanford University Perimeter Trail, Palo Alto,
California, June 2015 - March 2016
1450 Page Mill Road, California, September 2015 -
Ongoing.
Matadero Creek Rehabilitation Project, Palo Alto,
California. Ground Zone prepared the WPCP for the project which
is expected to start in the summer of 2016.
1085 Whipple Road, BART Hayward Maintenance Yard Complex,
Hayward, California, December 2014 - April 2015.
Sandoval Access Road, BART Hayward Maintenance Yard
Complex, Hayward, California, May 2015. Ground Zone prepared the
SWPPP for the project.
Caltrans Mococo Retrofit Project, Benicia Bridge (Highway
680 South bound Off Ramp), October 2014 - December 2015.
Caltrans San Pedro Bridge Replacement Project, Highway 1,
Pacifica, July 2014 - Ongoing.
Pilarcitos Bridge Reconstruction Project, Half Moon Bay,
October 2015 - November 2015
Capell Bridge Rehabilitation Project, Highway 128, Napa,
California, July 2015 - November 2015.
Highway 17 Drain Repair Project. Ground Zone prepared the
current the WPCP for the project.
Reconstruct Route HWY 880/92 Freeway Interchange, in
Hayward, Alameda; October 2010
Route 4, Highway Widening and Reconstruction, Somersville
Interchange, Contra Costa County; October 2010 - December 2010
Route 68 in Monterey, Construct Concrete Median Barrier;
October 2010 - January 2011
San Benancio Road/Route 68 Intersection Improvement;
October 2010 - December 2010
3170 Porter Drive, Palo Alto, California March 2016 -
Ongoing
Services - Industrial General Permit
Preparing and implementing SWPPPs
Implementing best management practices (BMPs)
Conducting site inspections and reporting
Field Sampling and analysis
Preparing Quality Assurance Project Plans for field
sampling and analysis plans
Collecting and submitting samples to the laboratory for
analysis
Preparing Annual Summary Reports.
Industrial General Permit - Project Experience
Storm Water Pollution Prevention Plan, Bay Polymer
Corporation, 44530 S. Grimmer Blvd, Fremont, California (Ground
Zone, October 2, 2014)
Storm Water Pollution Prevention Plan, All Cities
Landfill, 4001 Winton Ave, Hayward, California (Ground Zone,
October 15, 2015)
Storm Water Pollution Prevention Plan, Oakland Pallet Co., Inc, 2500 Grant Avenue, San Lorenzo, California (Ground Zone, July 6, 2017)